WWTP Khujand, Tajikistan
Generally, urban water supply and sanitation in Tajikistan is in bad condition due to the lack of maintenance since the break-up of the Soviet Union. EBRD and SECO started cooperation on water projects in Tajikistan in 2004 with the Khujand Water Supply Project Phase I. The City of Khujand (population 167'000) is the second largest city of Tajikistan. The project phase I was completed in 2008 and yielded promising results. Therefore, the EBRD and the SECO approved a second phase in 2009. Thanks to these two phases, the conditions of the water supply systems have improved substantially, while the wastewater sector is still in a very bad state therefore EBRD started the programme Khujand water supply improvement programme phase III which includes 3 Lot's and the contract for LOT-1 & LOT-2 is awarded to our company FELA Planungs AG from Switzerland for Rehabilitation of existing Wastewater Treatment plant (WWTP) LOT-1 and Rehabilitation of Pond System and Auxiliary Structures LOT-2.
The existing WWTP was built in the 1970’s. The mechanical and biological units are out of operation for more than 10 years. All electro-mechanical equipment has either been removed or is completely dilapidated and non-functional.
Expected results after implementation of the project will be a fully functioning Waste Water Treatment Plant and the impact of the project will improve living conditions and economic opportunities for the population of the city of Khujand.
Task:
Rehabilitation of Waste Water Treatment Plant (WWTP) and Rehabilitation of Pond System and Auxiliary Structures in Khujand. Supply and Installation of Equipment and Related Civil Works LOT 1 & LOT-2. In the frame work of Khujand water supply improvement programme (phase III)
Period:
September 2018 - September 2019
Location:
Khujand City, , Tajikistan
Civil Works:
-
Inlet structure, Screen building (coarse and fine screens) and admin complex.
-
Sand traps, Sand classifier and flow measurements.
-
Sludge pumping station including scum pit
-
Primary Clarifier
-
Bio-Ponds and Auxiliary Structures
Mechanical Installation:
-
7 Penstocks, 3 coarse screens, 3 fine screens, belt conveyer, screening press
-
12 Penstocks, 4 Sand Pumps + 1 mobile
-
4 Sludge Pumps
-
4 Primary clarifier with circular scrapers incl. swimming sludge removal system
-
Flow Measurements
Electrical and Control:
-
PCS/SCADA system
-
Internal, external electrical networks incl. cabinets / panels
-
Unitized transformer substation, power 10 kV / Transformer capacity 400 kVA
-
Power Transformer, 35 kV capacity 4000, 6300 kVA
Piping Networks:
-
Sludge Pipeline
-
Sewerage Network
-
Water Supply Network