Thermal Substations Tarnogrodskogo, Vinnytsia

Energy security is a major policy issue in Ukraine, and its dependency on external supplies is exacerbated by the low efficiency of energy use. In the city of Vinnytsia the "European Energy Award municipal energy management system" was successfully introduced in order to enhance the living conditions of the population and the energy independence of the country. The optimization of the district heating system operation for thermal substations improves the consumers' service standard and the energy efficiency.


Task:

Procurement of Thermal Substations (TS), SCADA system components and associated services for Ternogrodskogo district in Vinnytsia, Ukraine.


Period:

March 2016 - October 2016


Location:

Tarnogrodskogo, Vinnytsia, Ukraine

    Supply of:

  • Delivery of 68 factory assembled Thermal Substations

  • SCADA System components

  • Hydraulic and electrical connections between the different frames of the TS

  • Additional Service:

  • Supervising of the connecting the TS to the utility network

  • Testing and commissioning

  • Training of operating staff